A whole station is more than a building.
When a line is converted from metre gauge to broad gauge, its stations are effectively rebuilt. This package covered everything a passenger touches at Thiruthuraipoondi, Thillaivilagam and Muthupet: the station buildings themselves, passenger platforms and goods platforms, platform shelters, foot over bridges, toilets, drainage, cycle stands and the approach roads that connect each station to its town.
The Letter of Acceptance set a ten-month milestone programme, with the contract liable to termination if the first two milestones slipped — a schedule that demanded parallel working across all three yards. Structural work, steel shelter erection, finishing trades and external development ran side by side, and the Deputy Chief Engineer, Construction–III, Tiruchchirappalli certified the work as completed satisfactorily on 24.07.2019 with no dues outstanding.
Rates were founded on USSOR 2011 schedules across four annexures, tendered through IREPS e-tender 34-CE-CN-MS-2016-OT (MTK-118).