Road Under Bridges — LC 103, 72 & 69
Three RCC box road under bridges built in lieu of level crossings, with boxes cast beside the line and jacked into position under traffic blocks on running track.
Every railway package executed by the KCK group — road under bridges, a 45° skew road over bridge, major bridge rebuilding and complete station construction — for Southern, South Central and South Western Railway.
Every package on one ledger — the way a divisional works branch would keep it. Select a row to jump to its card.
| Pkg | Section | Work | Railway | |
|---|---|---|---|---|
| PKG·01 | Nagasamudram · Chakarlapalli · Pandiparthi | 3 road under bridges — LC 103, 72, 69 | South Western | ↓ |
| PKG·02 | Thiruvarur–Pattukkottai | Major bridges 217 & 224 — Agr No. 16 | Southern | ↓ |
| PKG·03 | Thiruvarur–Pattukkottai | Major bridges 233 & 251 — Agr No. 17 | Southern | ↓ |
| PKG·04 | Vayalpad–Kalikiri | 3 road under bridges — LC 104, 106, 115 | South Central | ↓ |
| PKG·05 | Vayalpad–Kalikiri | 3 road under bridges — LC 102, 103, 07 | South Central | ↓ |
| PKG·06 | Regadipalli–Vanganuru | Road over bridge — 45° skew, PSC 'I' girder | South Central | ↓ |
| PKG·07 | Thiruthuraipoondi · Thillaivilagam · Muthupet | 3 complete station yards | Southern | ↓ |
| PKG·08 | Tirupati | Station FOB, platform & service building works | South Central | ↓ |
| PKG·09 | Dharmavaram–Pakala & adjacent sections | 19 road under bridges — direct award to JV | South Central | ↓ |
Filter by type of work or by zonal railway. Packages with a dedicated page link through to the full story — photographs, drawings and the document trail.
Three RCC box road under bridges built in lieu of level crossings, with boxes cast beside the line and jacked into position under traffic blocks on running track.
Rebuilding of two major bridges for broad gauge with PSC 'U' girder superstructure, part of the four-bridge renewal on the converted line.
The second bridge package on the same corridor: two further major bridges rebuilt with PSC 'U' girders, including work over live waterways with river protection.
Three level crossings eliminated with RCC box RUBs, approach roads and retaining structures on the Vayalpad–Kalikiri section.
A companion package on the same section: three further crossings replaced with RCC box structures and finished road approaches.
A road over bridge carrying the road across the railway on a true 45° skew — 28.284 m skew spans over a 20 m square crossing — with PSC 'I' girders and RCC slab.
Station buildings, platforms, shelters, foot over bridges and every passenger amenity at Thiruthuraipoondi, Thillaivilagam and Muthupet. Certified complete 24.07.2019.
Foot over bridge, service building balance work, passenger platform, and watering and drainage arrangements at one of South India's busiest pilgrim stations.
Nineteen RUBs in lieu of manned and unmanned level crossings, awarded directly to Teja–MVVS–KCK (JV) under LOA dt. 10.10.2017 with a nine-month programme.
Eight of the nine packages were tendered to prime contractors and executed in full by KCK entities as sub-contractor on back-to-back terms — own finance, men, material and machinery, to the railway's rates, milestones and specifications. The nineteen-RUB package (PKG·09) was awarded directly to Teja–MVVS–KCK (JV) by South Central Railway headquarters, Secunderabad.
Each project page carries its own document trail — tender numbers, letters of acceptance, agreements and completion certificates — so the record speaks for itself.