Station Buildings & Passenger Amenities — KCK Infra Projects
Southern Railway · Gauge Conversion, Thiruvarur–Pattukkottai

Three complete stations, built from the ground up.

Station buildings, platforms, shelters, foot over bridges and every passenger amenity at Thiruthuraipoondi, Thillaivilagam and Muthupet — delivered as one package on a working gauge-conversion corridor.

Station yards3
Completion period10-month programme
Completed24.07.2019
Rate basisUSSOR 2011
The corridor

Three yards on the Thiruvarur–Pattukkottai line

The metre-gauge line between Thiruvarur and Pattukkottai was converted to broad gauge. At three of its station yards, the entire passenger-facing station — building, platforms and amenities — was constructed new under this package.

THIRUVARUR ⟵ ⟶ PATTUKKOTTAI THIRUTHURAIPOONDI STATION YARD 1/3 THILLAIVILAGAM STATION YARD 2/3 MUTHUPET STATION YARD 3/3
The work

A whole station is more than a building.

When a line is converted from metre gauge to broad gauge, its stations are effectively rebuilt. This package covered everything a passenger touches at Thiruthuraipoondi, Thillaivilagam and Muthupet: the station buildings themselves, passenger platforms and goods platforms, platform shelters, foot over bridges, toilets, drainage, cycle stands and the approach roads that connect each station to its town.

The Letter of Acceptance set a ten-month milestone programme, with the contract liable to termination if the first two milestones slipped — a schedule that demanded parallel working across all three yards. Structural work, steel shelter erection, finishing trades and external development ran side by side, and the Deputy Chief Engineer, Construction–III, Tiruchchirappalli certified the work as completed satisfactorily on 24.07.2019 with no dues outstanding.

Rates were founded on USSOR 2011 schedules across four annexures, tendered through IREPS e-tender 34-CE-CN-MS-2016-OT (MTK-118).

Contract attribution The Letter of Acceptance No. W.496/MTK/118/CN (7904) dt. 24.05.2017 was issued by Southern Railway to Sri A. Venku Reddy, Hyderabad. KCK Infra Projects, Kadapa executed the complete work as sub-contractor on a back-to-back basis under agreement dt. 01.06.2017, deploying its own finance, men, material and machinery.
Completed station building with entrance portico and paved circulating area
Completed station building with portico and circulating area · TTP–PKT section
Contract record

From e-tender to completion certificate

27.10.2016

E-tender published

Tender No. 34-CE-CN-MS-2016-OT (MTK-118), IREPS portal, CAO/Construction, Southern Railway, Egmore.

02.12.2016

Tenders opened

Technical bids opened; price bid followed on 08.05.2017.

24.05.2017

Letter of Acceptance issued

LOA No. W.496/MTK/118/CN (7904) — ten-month completion period with a milestone statement; contractor directed to meet Dy.CE/GC/III/TPJ and start immediately.

01.06.2017

Back-to-back sub-contract to KCK

K. Subba Rami Reddy, KCK Infra Projects, Kadapa takes on execution of the whole work with own finance, men, material and machinery.

11.08.2017

Contract agreement executed

Agreement No. 32/Dy.CE/GC-III/TPJ/TTP-PKT, Tiruchchirappalli.

24.07.2019

Work completed & certified

Work Completion Certificate issued by Dy. Chief Engineer, Construction-III, Tiruchchirappalli: completed satisfactorily, no dues against the contractor.

08.08.2019

Execution certified to KCK

Prime contractor's completion certificate records the work as executed by M/s KCK Infra Projects, Kadapa.

Scope of work

Nine trades, three yards, one programme

The subject line of the Letter of Acceptance reads like a checklist of everything a small station needs. Each element below was constructed at each of the three yards.

SCH·01

Station buildings

RCC-framed station buildings with booking, waiting and service areas, entrance porticoes and platform-side verandas.

SCH·02

Passenger platforms

New broad-gauge passenger platforms with finished surfacing and painted platform edges.

SCH·03

Goods platforms

Goods platforms and approach arrangements for freight handling at the converted yards.

SCH·04

Platform shelters

Structural-steel platform shelters fabricated and erected over the waiting lengths of each platform.

SCH·05

Foot over bridges

Steel foot over bridges with staircases, giving passengers safe crossing over the running lines.

SCH·06

Toilets

Toilet blocks with water supply arrangements for passengers and station staff.

SCH·07

Drainage

Surface and platform drainage across each yard and its circulating area.

SCH·08

Cycle stands

Covered cycle stands in the circulating areas serving daily commuters.

SCH·09

Approach roads

Approach roads and circulating areas connecting each station building to the public road network.

Site record

Twelve photographs from the three yards

The largest photographic record of any package in the profile — from structural work and shelter steel through to finished buildings, platforms and circulating areas.

Elevated view of a completed station yardCompleted
Elevated view across a finished yard — platform, station building and circulating area.
Station building front with porticoCompleted
Main station building with entrance portico and paved circulating area.
Finished platform with shelterCompleted
Finished passenger platform with shelter along the running line.
Platform shelter and building from track levelCompleted
Platform shelter and station building seen from track level.
Steel foot over bridgeCompleted
Steel foot over bridge and staircase spanning the yard.
Station building elevationCompleted
Station building elevation with finishes complete.
Platform-side veranda of station buildingCompleted
Platform-side veranda of the station building.
Masonry and RCC work in progressIn progress
Structural stage — masonry and RCC framing of a station building.
Platform shelter steelworkIn progress
Platform shelter steelwork during erection.
Circulating area under developmentIn progress
Circulating area and approach road under development.
Station building after plasteringIn progress
Station building after plastering, ahead of final finishes.
Long view along a finished platformCompleted
Long view along the finished platform and running line.

TODO: Photo captions describe what is visible; the three yards are not individually identifiable from the photographs. Have someone who was on site confirm which photos belong to Thiruthuraipoondi, Thillaivilagam and Muthupet, and adjust captions and stage tags where needed.

Document trail

On the record

Employer
Southern Railway · CAO/Construction, Egmore, Chennai
Executing division
Dy.CE/GC-III/TPJ · Tiruchchirappalli
E-tender
34-CE-CN-MS-2016-OT (MTK-118) dt. 27.10.2016
Letter of Acceptance
W.496/MTK/118/CN (7904) dt. 24.05.2017
Agreement
32/Dy.CE/GC-III/TPJ/TTP-PKT dt. 11.08.2017
Rate basis
USSOR 2011 · Annexures A–D
Completion period
10 months · milestone programme
Completion certified
24.07.2019 · no dues outstanding