Where the road has to go over instead of under — multi-span structures on pile foundations, combining precast concrete and composite steel decks across live running lines.

3Spans
99mTotal girder length
45°Skew crossing
2Lane carriageway

The work

Sometimes the road cannot go under.

A road under bridge needs depth — room to drop the carriageway below the formation and drain it. Where the ground water is high, the embankment is shallow, or the road carries heavy traffic that cannot take a dip, the crossing has to go over the top instead.

That means a bridge: piled foundations either side of the railway, piers, and girders long enough to clear every track with the statutory headroom for overhead electrification below.

Nothing may be dropped, and nothing may foul the overhead line. Every lift happens inside a block, at night, with the traction current off.

We built the two-lane road over bridge at Km 347/33–35 between Regadipalli and Vanganur stations for South Central Railway's Construction Organisation — three spans, on piles, crossing the railway at forty-five degrees.

Piers and girders of the road over bridge under construction

The structure

Three spans, two girder types, one crossing.

Drawn to scale from the span arrangement in the letter of acceptance. The centre span is a composite girder — steel ‘I’ girders carrying an RCC deck slab — because it has to reach across every track in one clear span. The flanking spans are precast prestressed concrete.

PSC girder Composite girder — steel ‘I’ + RCC deck Pile foundation
RAILWAY — DHARMAVARAM–PAKALA 2-LANE CARRIAGEWAY 28.284 m 42.496 m 28.284 m (20.0 m square) (30.0 m square) (20.0 m square) PILE FOUNDATIONS THROUGHOUT

Elevation drawn to scale from the span arrangement recorded in the letter of acceptance dated 16.08.2016.
Span lengths and girder types are as specified. Pier heights, pile depths and deck width are indicative only.

The hard part

The bridge crosses the railway at 45 degrees.

Read the contract dimensions carefully and a detail emerges: every span is quoted twice — once as a skew length and once as a square length. 28.284 m and 20.0 m. 42.496 m and 30.0 m.

Those are not two different measurements of the same thing by accident. 28.284 is 20 × √2. The road meets the railway at forty-five degrees, so each girder has to be roughly forty per cent longer than the distance it actually spans across the track.

A skew crossing is harder in every direction. Girders are longer and heavier for the same clearance. The deck is a parallelogram, not a rectangle. Load distributes unevenly towards the obtuse corners, bearings have to be set to the skew, and the pier caps sit at an angle to the deck they carry.

28.284 m  ÷  20.0 m  =  1.4142
cos⁻¹ (1 ÷ 1.4142)  =  45.0° Skew angle derived from the contract span dimensions
RAILWAY ROAD DECK 30.0 m square 42.496 m skew 45°

Scope of works

Six priced schedules.

The contract was let against six separate schedules, which between them describe the whole structure from pile to parapet.

A

General civil works

Earthwork, substructure and general items rated against the Unified Standard Schedule of Rates 2010.

B

Casing pipe & reinforcement

Providing, fabricating and installing casing pipe and reinforcement steel for the bored pile foundations.

C

Structural steel

Fabrication and erection of structural steelwork as non-schedule items.

D

Composite girder

The 42.496 m centre span — steel ‘I’ girders with an RCC deck slab acting compositely.

E

Non-schedule items

Bearings, expansion joints, crash barriers, railings, drainage and finishing items.

F

Cement

Cement supply for the pile foundations, substructure, PSC girders and deck slab.

Project record

Regadipalli–Vanganur Road Over Bridge

Railway
South Central RailwayChief Administrative Officer (Construction), Secunderabad · Guntakal Division
Location
Km 347/33–35, between Regadipalli and Vanganur stationsAndhra Pradesh
Structure
Two-lane road over bridge on pile foundations1 × 28.284 m PSC girder + 1 × 42.496 m composite girder (steel ‘I’ girder with RCC deck slab) + 1 × 28.284 m PSC girder
Tender
Notice No. 04/CAO/C/SC/2016 dated 05.02.2016Opened 14.03.2016 · negotiated offer 04.08.2016
Acceptance
16.08.2016Letter No. W.CON.496/AG/ROB/RLL-VRN/S894/WC.3
Agreement
54H/CAO/C/SC/2016 dated 24.11.2016
Commenced
10.02.2017
Completed
10.11.2018Extended to 31.12.2018 without penalty — completed ahead of the extended date
Performance
Certified satisfactoryWork completion certificate issued by Dy. Chief Engineer/Construction, Guntur

Get in touch